TEMPO.CO, Jakarta - Transjakarta flyover of Corridor XIII which is a 9.3-km Ciledug-Tendean route is targeted to be operational in June.
PT Transjakarta Director, Budi Kaliwono, said they will hold a trial in two months after the road structure construction is completed in February.
“We need a two-month trial,” he said, Friday (1/6).
Budi assessed that the flyover construction is quite fast.
“June is a reasonable month to operate the corridor,” he added.
Meanwhile, Jakarta Head Dept. of Bina Marga, Yusmada Faisal, explained that the road structure construction progress has reached 97 percent. At this moment, the remaining works are asphalting, road marking, and returning the initiate road condition under the flyover.
“Our target is to complete it next month. We also cooperate with existing developer to arrange the surrounding,” he closed.