PLN to Fix 69 Electricity Substations Damaged by Mount Semeru Eruption

Translator

Antara

5 December 2021 21:45 WIB

Satellite image of volcanic ash movement (in yellow curve) of Mount Semeru which erupted on Saturday afternoon, December 4, 2021. Photo : BMKG

TEMPO.CO, JakartaState Electricity Enterprise (PLN) targets that 69 of 79 electricity substations can be reactivated again tomorrow, as currently they are still out of order due to Mount Semeru eruption in Lumajang, East Java.

"Of the 79 transformers that cover 22,826 customers, we can normalize 69 transformers," PLN's Senior Distribution Manager for East Java Distribution Main Unit Adriansyah said at a press conference on Sunday.

He explained that the restoration of the remaining 10 electrical substations would be conducted once the eruption of Mount Semeru slowed down.

PLN has deployed a team  in the affected areas to restore the condition of 10 electrical substations. However, the restoration effort was halted on Sunday owing to another eruption of the volcano.

"It's raining of thick volcanic ash, so we are not able to restore the electricity network," he remarked.

As of Sunday at 10 a.m.local time, PLN has managed to reactivate 33 electricity substations, put of a total of 112 electricity substations affected by the eruption of Mount Semeru.

Adriansyah said that his office would try its best to fix the condition of the existing electricity networks in areas affected by the disaster.

He informed that the workers was not able to enter the affected area because Gladak Perak Bridge had collapsed, preventing vehicles from passing.

The company plans to pull the electricity transmission network and build a new 300 meter connection to the Ampel Gading feeder from Supit.

"Today we are ready to move to build a 300-meter pole planting," he concluded.

Mount Semeru, the highest mountain on the island of Java, has erupted since Friday, December 3.

Head of the National Disaster Mitigation Agency Lieutenant General Suharyanto said on Sunday, said that the eruption of Mount Semeru had claimed 13 lives as of Sunday at 9:20 a.m. local time.

Read: Mount Semeru: Social Affairs Minister Visits Lumajang to Ensure Aid Distribution

ANTARA



PLN to Build Tanah Baru Power Plant, Gets the Lowest Bid in History

2 hari lalu

PLN to Build Tanah Baru Power Plant, Gets the Lowest Bid in History

Total Eren and PT Adaro Power have won the tender for the development of the Tanah Laut Wind Power Plant (PLTB) in South Kalimantan.


PLN, Hyundai Kefico Collaborate to Develop Battery Swapping Station for Electric Motorcycle

2 hari lalu

PLN, Hyundai Kefico Collaborate to Develop Battery Swapping Station for Electric Motorcycle

State power company PT PLN (Persero) is collaborating with Hyundai Kefico and Consortiums to develop Battery Swapping Station for Motorcycles (SPBKLU.


PLN Says Indonesia's Electricity Consumption Lower than Neighboring Nations

7 hari lalu

PLN Says Indonesia's Electricity Consumption Lower than Neighboring Nations

State-run electricity firm PLN official, Muhammad Munif Budiman, said Indonesia's electricity consumption is low compared to neighboring countries.


Clean Energy; ESDM Ministry to Distribute 680,000 Rice Cookers

7 hari lalu

Clean Energy; ESDM Ministry to Distribute 680,000 Rice Cookers

The Energy and Mineral Resources (ESDM) Ministry planned to distribute 680,000 units of electric rice cookers to support the use of clean energy.


Minister Airlangga Optimistic Indonesia Can Be 'King of Green Energy'

8 hari lalu

Minister Airlangga Optimistic Indonesia Can Be 'King of Green Energy'

Indonesia's Coordinating Minister for Economic Affairs Airlangga Hartarto says the country could become a king in the green energy sector.


PLN UID, Jakarta Acting Governor Discuss Preparation for Extreme Weather

8 hari lalu

PLN UID, Jakarta Acting Governor Discuss Preparation for Extreme Weather

PLN Distribution Main Unit (UID) met with Jakarta acting governor Heru Budi Hartono to discuss preparation for extreme weather.


PLN Restores Electricity System 36 Hours after Cianjur Earthquake

9 hari lalu

PLN Restores Electricity System 36 Hours after Cianjur Earthquake

PLN says the electricity system in Cianjur is back running at 100-percent capacity 36 hours after the earthquake.


Electricity System Affected by Cianjur Earthquake Has Recovered 100 Percent: PLN

9 hari lalu

Electricity System Affected by Cianjur Earthquake Has Recovered 100 Percent: PLN

The electricity system affected by the earthquake in Cianjur, West Java, has recovered 100 percent, stated state electricity firm PLN.


PLN and Sumitomo Collaborate to Accelerate Energy Transition in Indonesia

13 hari lalu

PLN and Sumitomo Collaborate to Accelerate Energy Transition in Indonesia

PT PLN (Persero) and Sumitomo Corporation are collaborating to accelerate the energy transition in Indonesia.


PLN, ADB to Plan Early Retirement for Independent Coal Power Plants

14 hari lalu

PLN, ADB to Plan Early Retirement for Independent Coal Power Plants

PLN with Asian Development Bank (ADB) plans early retirement of coal power plants through the Energy Transition Mechanism (ETM) scheme.