High-Speed Rail Cost Overrun in Final Negotiation Phase, says KCIC

16 January 2023 12:30 WIB

TEMPO.CO, Jakarta - The Kereta Cepat Indonesia Cina (KCIC) corporate secretary Rahadian Ratry on Sunday evening said the developer of the Jakarta-Bandung high-speed rail is currently waiting for the completion of the project’s cost overrun discussion, which he said is entering the final phase. 

"Regarding the discussion of cost overruns, we are currently entering the final stage of negotiations between the consortium and the governments of Indonesia and China," Rahadian said to Tempo on January 15. 

Rahadian also explained developments regarding state capital injection (PMN) that was still in the process of being distributed from Indonesian shareholders to KCIC. The development of KCJB operational readiness is currently still ongoing and faces a tight launch schedule of June 2023. 

Facilities that are going to be built in one of Indonesia’s ambitious projects, he added, focus on commuter accessibility, with some examples being the sky bridge that will connect the LRT station and the high-speed rail Halim Station. Other facilities include bridges connecting the Deltamas housing to the Karawang station, and another pedestrian accessway from Kota Baru Parahyangan to the train station. 

“The private sector will also contribute to constructing access ways to the Jakarta-Bandung high-speed rail. This is surely a positive aspect in increasing public mobility,” he explained. 

MOH KHORY ALFARIZI

Click here to get the latest news updates from Tempo on Google News



Jokowi Summons Officials over WIKA's Whoosh Project Losses

2 hari lalu

Jokowi Summons Officials over WIKA's Whoosh Project Losses

President Jokowi summoned officials involved in the Jakarta-Bandung High-Speed Railway or Whoosh project to the palace today, July 24.


KCIC Responds to WIKA's Claims of Losses on Whoosh Bullet Train Project

10 hari lalu

KCIC Responds to WIKA's Claims of Losses on Whoosh Bullet Train Project

PT Kereta Cepat Indonesia-China (KCIC) addressed WIKA's statements regarding financial losses attributed to the Whoosh project.


Indonesian High-Speed Train Whoosh Records 4mn Passengers in 9 Months of Operation

11 hari lalu

Indonesian High-Speed Train Whoosh Records 4mn Passengers in 9 Months of Operation

Whoosh has sold over 4 million tickets since it operated commercially last year on October 17.


Whoosh High-speed Train Has Served 4 Million Passengers Since Its Operation Began in 2023: KCIC

13 hari lalu

Whoosh High-speed Train Has Served 4 Million Passengers Since Its Operation Began in 2023: KCIC

PT Kereta Cepat Indonesia China (KCIC) stated that the Whoosh fast train has served 4 million passengers since it began operating on October 17, 2023.


Whoosh Logs 20% Hike in Passengers During 2024 School Holiday

25 hari lalu

Whoosh Logs 20% Hike in Passengers During 2024 School Holiday

Whoosh recorded a 20 percent hike in passengers since mid-June 2024, in line with the school holidays.


Whoosh Fast Train Offers 20% off Tickets

34 hari lalu

Whoosh Fast Train Offers 20% off Tickets

KCIC offers a ticket discount of 20 percent for Whoosh fast train on June 22, to celebrate Jakarta anniversary.


Why the Railway Corruption Case Grinds to a Halt

38 hari lalu

Why the Railway Corruption Case Grinds to a Halt

The corruption case at the Directorate-General of Railway fails to implicate any of the big names mentioned in court. The KPK is at death's door.


KAI Closes Down 19 Illegal Railroad Crossings in West Java

51 hari lalu

KAI Closes Down 19 Illegal Railroad Crossings in West Java

KAI of the Bandung Operational Area II closed 19 unregulated railroad crossings in West Java during the January-June 2024 period.


Whoosh Sees Spike in Sales Ahead of Long Weekend

8 Mei 2024

Whoosh Sees Spike in Sales Ahead of Long Weekend

KCIC will operate a total of 48 Whoosh high-speed train trips during the long weekend period from May 9-12, 2024.


High-speed Rail Whoosh Offers 48 Trips per Day, Tariff Starting at Rp150,000

4 Mei 2024

High-speed Rail Whoosh Offers 48 Trips per Day, Tariff Starting at Rp150,000

High-speed rail Whoosh has set 48 trips per day in May 2024 with the tariff starting from Rp150,000.