Jakarta-Bandung High-Speed Rail Concession Extended

27 January 2023 20:40 WIB

TEMPO.CO, JakartaThe Indonesian government has recently approved the extended concession period for the Jakarta - Bandung high-speed rail project from 50 years to 80 years. The company overseeing the ambitious project, PT Kereta Cepat Indonesia China (PT KCIC) had initially pitched the concession extension in December 2022. 

This was revealed by the Coordinating Minister of Maritime Affairs and Investments Luhut Pandjaitan. 

“It is in effect,” said Luhut to journalists on Thursday, January 26, 2023.

Behind the Ambitious Project's Dynamics

The Transportation Ministry has the authority to extend the high-speed rail’s concession permit to 80 years as previously stated by the Minister of Transportation Budi Karya Sumadi. Minister Budi said that an extension may be granted if KCIC increases the value of its investment in the project. 

  1. Initial agreement

The concession agreement between the government and KCIC was originally regulated in Concession/Cooperation Agreement No. HK.201/1/21/Phb 2016 Amendment and Restatement of the Concession Agreement/Cooperation Agreement No. PJ 22/2017.

The agreement stated that the investment value financed by KCIC was US$5.9 billion with a concession period of 50 years from the date of operation of the infrastructure and facilities. The handover will be conducted at the end of the concession period, however, five years later, in a letter to the Ministry of Transportation dated August 15, 2022, KCIC Director requested that adjustments be made to the concession period for the High-Speed Rail project. 

The letter stated that the extension of the concession period was needed to meet the project's cost overrun of roughly Rp21.4 trillion. The cost overrun is based on the calculation of the Financial and Development Supervisory Agency (BPKP).

  1. The concession extension from 50 to 80 years 

KCIC had asked the government to extend the KCJB management concession period from 50 to 80 years. This information was revealed by the Transporation Ministry's director general of railways Risal Wasal in a hearing with members of Commission V House of Representatives (DPR) on December 8, 2022. 

According to Risal, KCIC asked the Transportation Ministry to make adjustments to the concession period for the high-speed rail project as a consequence to numerous obstacles that caused changes in the project's business feasibility.

  1. The reason behind the 30-year extension period 

According to Risal, there are three reasons that underline the concession extension. The first is to improve the fast rail’s feasibility indicators in meeting the cost overrun funding. That way, the project can be completed on time.

The second reason is to maintain the continuity of the Jakarta-Bandung high-speed rail project in order to maximize the project's positive impact in various aspects such as social and economic, and state revenue contributions.

The third reason is to strengthen bilateral relations between China and Indonesia.

The high-speed rail project that will connect Java Island’s two major cities is scheduled to be operated for the public in June 2023.

HENDRIK KHOIRUL MUHID

Click here to get the latest news updates from Tempo in Google News



Whoosh Offers New Dining Cars for Passengers, Only Cash Transactions Available

16 hari lalu

Whoosh Offers New Dining Cars for Passengers, Only Cash Transactions Available

KCIC is working with Indomaret to provide a wide selection of food and beverages during Whoosh trips.


KCIC Provides Facilities for Eid Homecoming Travelers

18 hari lalu

KCIC Provides Facilities for Eid Homecoming Travelers

Indonesian high-speed rail company PT KCIC is providing several facilities for passengers of Whoosh high-speed train during Eid homecoming period.


The High-Speed Train Bottomless Pit

23 Februari 2024

The High-Speed Train Bottomless Pit

The finances of Indonesian railroad company KAI are suffering because of having to operate the Jakarta-Bandung high-speed train.


Whoosh High-speed Train Passenger Traffic Up 50 Percent on Chinese New Year

11 Februari 2024

Whoosh High-speed Train Passenger Traffic Up 50 Percent on Chinese New Year

The number of passengers using the Jakarta-Bandung Whoosh High-Speed train increased by 50 percent during the Chinese New Year.


Whoosh Denies Rumor of Low Passengers Behind Dynamic Pricing Policy

29 Januari 2024

Whoosh Denies Rumor of Low Passengers Behind Dynamic Pricing Policy

Eva Chairunisa denied the rumors of Whoosh dynamic pricing caused by the low occupancy rate of the high-speed train.


Jakarta-Bandung High-speed Train to Apply Dynamic Ticket Pricing Starting February 3

28 Januari 2024

Jakarta-Bandung High-speed Train to Apply Dynamic Ticket Pricing Starting February 3

Jakarta-Bandung high-speed train ticket prices will become dynamic starting February 3, 2024.


KCIC Denies Whoosh Revenues Far Below Projections

19 Januari 2024

KCIC Denies Whoosh Revenues Far Below Projections

PT Kereta Cepat Indonesia China (KCIC) denies reports that revenues from Whoosh in 2023 were far below the company's projections.


KCIC Provides 'Park and Ride' Facilities at Whoosh High-speed Train Stations

10 Januari 2024

KCIC Provides 'Park and Ride' Facilities at Whoosh High-speed Train Stations

KCIC provides safe and comfortable 'park and ride' facilities at stations of the Jakarta-Bandung "Whoosh" high-speed train.


Whoosh Serves 220,227 Passengers During Christmas and New Year Holiday

3 Januari 2024

Whoosh Serves 220,227 Passengers During Christmas and New Year Holiday

Throughout the 12-day Christmas and New Year holidays, the Whoosh high-speed train has served over 220,227 passengers.


Whoosh Adds Service to 48 Trips per Day During New Year Holiday

30 Desember 2023

Whoosh Adds Service to 48 Trips per Day During New Year Holiday

KCIC recorded that Whoosh high-speed rail had transported 20,000 passengers in 384 trips during the holiday festivity.