Newly Introduced East Java Dam Cost Overrun Reach a Total of Rp2.5 trillion

21 December 2022 12:34 WIB

TEMPO.CO, Jakarta The construction of the East Java Semantok Dam, located specifically in Nganjuk Regency, is officially one of the national strategic projects under the Joko “Jokowi” Widodo - Ma’ruf Amin administration that saw a cost overrun from the initial Rp805 billion to Rp2.5 trillion as it was introduced today. 

The rising cost was explained by the Head of the Brantas River Basin Center (BBWS) Haeruddin C. Maddi on December 20. 

“It is due to the changes in the foundation structure and heap volume,” said Maddi on Tuesday. “In general terms, that was what caused the cost to rise.”

President Jokowi officially inaugurated the dam and asserted its role in supporting agricultural production in the future. “If in normal days harvest only comes once or twice. [In the future] harvests can be twice and three times,” said the President today. 

In inaugurating the dam that started construction in 2017, the President commented on the cost of the dam was “Not an insignificant amount of money.”

The cost increase happened because of the change in the type of stockpile which also increased its volume. Costs also increased due to changes in the location of the stone quarry and adjustments to the relocation of provincial roads.

Citing the official website of the Committee for the Acceleration of Priority Infrastructure Provision (KPPIP), the Semantok Dam was initially set to have a total investment of Rp805 billion, sourced from the State Budget before the cost overrun. The dam is planned to have a capacity of 17.63 cubic meters and can irrigate 1,554 hectares of land and generate 1.01 Megawatts of electricity.

FAJAR PEBRIANTO

Click here to get the latest news updates from Tempo on Google News



Kediri Dhoho Airport to Start Operations on April 5

13 hari lalu

Kediri Dhoho Airport to Start Operations on April 5

Dhoho Airport in Kediri, East Java is set to commence its inaugural flight on Friday, April 5.


7 Recommended Tourist Destinations Along the Southern Coastal Lane of Java

15 hari lalu

7 Recommended Tourist Destinations Along the Southern Coastal Lane of Java

Here are seven recommended tourist destinations along the southern coastal lane of Java.


Jokowi Unveils Gumbasa Dam, Irrigation after Rp1.25tn Rehabilitation Completed

21 hari lalu

Jokowi Unveils Gumbasa Dam, Irrigation after Rp1.25tn Rehabilitation Completed

Jokowi unveils the rehabilitated and reconstructed Gumbasa Dam and Irrigation Area in Sigi Regency, Central Sulawesi,


Another Strong Earthquake Jolts Tuban and Its Neighbors

26 hari lalu

Another Strong Earthquake Jolts Tuban and Its Neighbors

Another earthquake centered in the Java Sea with a stronger magnitude of 6.5 jolted Tuban and its surroundings on Friday afternoon, March 22.


BMKG Logs Eight Aftershocks Post Java Sea Earthquake

26 hari lalu

BMKG Logs Eight Aftershocks Post Java Sea Earthquake

The Meteorology, Climatology, and Geophysics Agency (BMKG) recorded that there had been at least eight aftershocks following the Java Sea earthquake.


Jokowi Inaugurates 33 Roads Worth Rp925bn in East Java

40 hari lalu

Jokowi Inaugurates 33 Roads Worth Rp925bn in East Java

President Jokowi inaugurated the construction and repair on 33 road infrastructure, totaling 275 kilometers in Madiun, East Java.


Kiara, Walhi Call for an End to Exploitation of East Java Waters

40 hari lalu

Kiara, Walhi Call for an End to Exploitation of East Java Waters

Walhi says marine areas in East Java are threatened after the passing of the Regional Regulation on the Regional Spatial Plan for East Java.


Jokowi, Prabowo Inspect Fighter Jets at Iswahjudi Magetan Air Force Base

40 hari lalu

Jokowi, Prabowo Inspect Fighter Jets at Iswahjudi Magetan Air Force Base

President Jokowi kick-started his working visit today to East Java by inspecting the national primary weapon system at Iswahjudi Air Force Base.


Six Months of Golden Visa, Immigration Records Seven Applications in East Java

42 hari lalu

Six Months of Golden Visa, Immigration Records Seven Applications in East Java

Golden Visa can be applied for since August 2023 with growing enthusiasm in just 6 months.


Govt Builds Dams in Bogor to Curb Floods in Bekasi and Karawang: Minister

45 hari lalu

Govt Builds Dams in Bogor to Curb Floods in Bekasi and Karawang: Minister

The government is building two dams in Bogor District, West Java, to reduce flood risks in Bekasi and Karawang